Stoda Residence Gated Community, Sheraton Area
Project Description:
Infinity Group for General Construction & Supplies (IGC) carried out the electrical infrastructure works for the project, including the supply and installation of the main electrical systems to ensure efficient and continuous operation.
Scope of Work:
Supplying and installing the main distribution panel (17 cells) with a medium voltage of 24 kV.
Supplying and installing electrical kiosks with the following capacities:
1500 kVA
1000 kVA
500 kVA (22/0.4 kV)
Supplying and installing SF6 Ring Main Units (3+1).
Laying medium voltage cables (18/30 kV) and low voltage cables.
Supplying and installing street lighting poles and grounding systems.
Constructing the distribution building and executing all electromechanical works.
Execution Outcome:
These works contributed to equipping the project with reliable electrical systems in accordance with the highest standards of quality and safety, ensuring the sustainability and efficiency of facility operations.